Box Build & Assembly

Material issue to assembly line, CTP/CTQ, Functional Testing, Visual & Final Inspection.
Material Issue to Assembly Line · 0 queuedCTP / CTQ Stations · 0 queuedFunctional Testing Machines · 0 queuedVisual Inspection · 0 queuedFinal Inspection · 5 queued

Material Issue to Assembly Line — BoM verification; material check-in at first assembly station (PCBA lower assembly).

No boards currently at this station.

CTP / CTQ Stations — Critical-to-process & critical-to-quality data capture; PCB/BOP mapping to FG material.

No boards currently at this station.

Functional Testing Machines — Machine data capture for test result; NG sent for rework.

No boards currently at this station.

Visual Inspection — Check-out for process completion; quality checksheet captured.

No boards currently at this station.

Final Inspection — Check-out for process completion; quality checksheet captured.

Serial NoJob OrderStationStatusLog Result
WO-2607-001-B001 WO-2607-001 Final Inspection completed No action pending
WO-2607-001-B002 WO-2607-001 Final Inspection completed No action pending
WO-2607-004-B001 WO-2607-004 Final Inspection completed No action pending
WO-2607-004-B002 WO-2607-004 Final Inspection completed No action pending
WO-2607-004-B003 WO-2607-004 Final Inspection completed No action pending

Recent Activity

TimeJob OrderBoardStationResultOperatorRemarks
2026-07-21 23:49 WO-2607-004 WO-2607-004-B003 Final Inspection ok K. Nair Passed.
2026-07-22 00:49 WO-2607-004 WO-2607-004-B002 Final Inspection ok R. Verma Passed.
2026-07-22 01:49 WO-2607-004 WO-2607-004-B001 Final Inspection ok A. Sharma Passed.
2026-07-22 12:49 WO-2607-001 WO-2607-001-B002 Final Inspection ok R. Verma Passed.
2026-07-22 13:49 WO-2607-001 WO-2607-001-B001 Final Inspection ok A. Sharma Passed.